The World's Largest "Artificial Sun" Installs Its 7th Vacuum Vessel Module, Installation Progress Exceeds Three-Quarters
IT Home, November 28 — On November 26 local time in France, the 7th vacuum vessel module of the world's largest "artificial sun," the International Thermonuclear Experimental Reactor (ITER) tokamak device — Sector Module 9 — completed its integrated lifting and was precisely positioned.
ITER is being built jointly by the European Union, China, Russia, the United States, Japan, South Korea, and India, at a site in southern France. This major international scientific project aims to simulate the nuclear fusion process that makes the sun shine and generate heat, and to explore the commercial feasibility of controlled fusion technology; it is also known as the world's largest "artificial sun."
According to an article published by China National Nuclear Corporation (CNNC) on November 27, this was the first double-side-restricted lifting of an ITER vacuum vessel module, coordinated by the CNNC Engineering consortium leading an international team. With this, the ITER vacuum vessel module assembly progress has exceeded three-quarters. The ITER vacuum vessel consists of 9 sector modules, each corresponding to 40 degrees.

Compared with previous installations, this was the first "restricted on both sides" lifting, in which the thousand-ton module had to complete descent, attitude adjustment, and precise positioning within the space defined by existing structures. Hu Xin, project leader of the Sector Module Sub-Assembly (SMSA) project, explained that the working space is very narrow, which affects the lifting path, the module's attitude in the air, and the precision requirements for lifting operations.

According to official introductions, the components of Sector Module 9 are more complex than those of previous modules, with uneven gravity distribution; before entering the predetermined position, it was first necessary to grasp the accurate spatial relationship between the module to be installed and the surrounding components.
According to officially released information, theoretical calculations show a gap of about 50mm on each side between Sector Module 9 and the adjacent modules, but during actual lifting the module exhibits slight verticality deviation and swaying, which may reduce the safety margin to 20-30mm per side.
Measurement engineer Yuan Zhong explained that before lifting, the project team collected geometric data of the relevant on-site structures and fed them into a model to carry out 3D virtual assembly. Lifting engineer Zhu Xiaoqian stated that the civil cable tray on the east side of the building is adjacent to the transfer path of Sector Module 9 and also poses a collision risk; after the test lift, the verticality of the module in a free state will be measured, and then compared against the lifting path and the building environment.
IT Home notes that this lifting imposed higher verticality requirements on the module than before: once the verticality deviation exceeds 6mm, combined with the swaying generated during displacement, the module is prone to interfering with the already-installed components on both sides during descent.
On November 25, Sector Module 9 was transferred from the assembly hall to above the main pit, and in the early hours of November 26 it began descending toward the predetermined position. The Construction Work Package (CWP) department team tracked load, pressure, clearance, and module tilt in real time.
From pre-assembly to lifting and positioning, Sector Module 9 took about 5.3 months, the shortest construction period to date. With this module in place, only the last two modules remain for ITER vacuum vessel sector module installation — the only 2 of the 9 modules with irregular configurations.

Related Articles
- The nuclear power base with the largest total installed capacity under construction and in operation worldwide: Tianwan Nuclear Power Unit 7 successfully connected to the grid for the first time
- New progress in "artificial sun" construction: China's compact fusion energy experimental device campus delivered for use
- New breakthrough! China achieves "fully domestic" krypton isotope thickness measurement sources
- Safety performance ranks in the global first tier, CNNC's Hualong One Version 2.0 innovation achievements unveiled
- China's nuclear insurance achieves local model pricing and RMB local currency settlement for the first time
- CNNC's first offshore wind power project installs its first pile at sea, supplying 1.034 billion kWh of energy annually